Illustrative sample report
Independent residential development project audit
Decision gate: additional funding decision
01 · Executive summary
Decision at the gate
Illustrative conclusion: consider additional funding after reconciling remaining work, contractual commitments and the cost-to-complete forecast. In this fictional example, there is not enough evidence to confirm the requested amount without qualifications.
| Metric | Baseline | Illustrative forecast | Variance |
|---|---|---|---|
| Commissioning date | Q4 2027 | Q1 2028 | +3 months |
| CAPEX budget | RUB 12.0bn | RUB 12.9bn | +RUB 0.9bn / 7.5% |
| Cost to complete | — | RUB 4.1bn | Not reconciled to a consolidated schedule |
- Schedule: the assumed delay is linked to utility readiness and available work fronts.
- Budget: the forecast exceeds the limit; the increase has not yet been allocated across packages and contracts.
- Governance: there is no single decision log linking project changes, CAPEX and approvals.
02 · Decision gate
Readiness for the next decision
This review tests the move into the next funding period: are schedule, remaining cost and commitments supported well enough to make the decision?
| Criterion | Status | What to check |
|---|---|---|
| Project economics | Needs reconciliation | Align the current model with the programme |
| Critical path | At risk | Confirm utility dates, access and available work fronts |
| Cost to complete | Unconfirmed | Reconcile remaining quantities, contracts and forecast to completion |
| Contractual commitments | Needs reconciliation | Consolidate contracts, changes, advances, claims and retentions |
The stage-gate review records the original decision and assumptions, checks current-stage data, assesses how variances affect the next decision, and defines transition conditions and owners.
03 · Schedule and CAPEX
Variances need one integrated forecast
In this example, the planned commissioning date moves by three months. To confirm the impact, the current programme needs logic links, progress as of the review date and remaining durations.
| Programme milestone | Plan | Illustrative status | Check |
|---|---|---|---|
| Utility networks | June 2027 | Expected completion: August 2027 | Confirm scope, resources and work-front release dates |
| Finishes | September 2027 | Float between sections is shrinking | Reconcile productivity assumptions and available work fronts |
| Commissioning | Q4 2027 | Risk of moving to Q1 2028 | Check scenarios and commissioning procedures |
An aggregate CAPEX figure does not confirm the forecast. Remaining quantities, contractual commitments, project changes, indexation and the cost of delay need to reconcile.
04 · Contracts and risks
Risks that affect the decision
| Risk | Early indicator | Action |
|---|---|---|
| Utility network slippage | Work-front release dates are not confirmed | Set a weekly plan with client and general contractor owners |
| Higher cost of remaining work | Remaining quantities are not tied to completed work and contract rates | Prepare a line-by-line balance and validate the calculation |
| Changes to scope are scattered | Correspondence has not been consolidated into a log | Record reason, amount, schedule impact, decision and contract status |
| Funding decision pack is incomplete | Key model assumptions are unconfirmed | Collect documents with owners and version dates |
This illustration does not include source documents, interviews, a site visit, cost-plan review, legal contract analysis or a recalculation of the financial model. A remote document review does not confirm the physical condition of the site.
05 · 30-day action plan
Actions and close-out criteria
| Timing | Action | Close-out criterion |
|---|---|---|
| Days 1–3 | Freeze aligned versions of the programme, budget, model and contract log | Document pack with owners and dates |
| Days 1–7 | Reconcile remaining quantities and cost to complete | Package-level schedule with sources and ranges |
| Days 1–7 | Confirm the critical path and utility scenarios | Linked programme, risk milestones and mitigations |
| Days 5–10 | Consolidate contractual commitments and changes | Commitments reconcile to the CAPEX forecast |
| Days 10–20 | Recalculate scenarios and hold a gate review | Decision log with owners and dates |
| Days 21–30 | Prepare the funding decision pack | Decision with conditions, limits and triggers |
06 · Sources and limitations
What supports the findings
In a real report, each variance is linked to a document, version date and data owner. Confirmed facts, the team’s forecast and the auditor’s assessment are kept distinct. Findings without supporting evidence are marked as preliminary.
- Programme: baseline, progress, remaining durations and work-front constraints.
- CAPEX: approved budget, actuals, commitments and cost to complete.
- Contracts: agreements, changes, payments, claims and remaining commitments.
- Economics: financial model and scenarios with key assumptions.
- Risks: owners, mitigations, review dates and escalation triggers.
This sample demonstrates the reasoning format and report structure. In a real audit, findings depend on the materials provided, interviews and agreed scope. The initial conversation takes 30 minutes and requires no documents.